Construction material procurement 3x faster
- Prepayment became 4.9 times faster
- Postpaid purchasing became 3 times faster
- Automated material procurement for sites
What a bill of quantities is in construction, how it differs from estimates and specifications, where quantities come from, and what state expertise requires.
The statement of work volumes (SWV) is a list of work items and materials for a construction project: name, unit of measure, quantity. It contains no prices, which is the main difference from an estimate: the statement answers what is being done and in what quantity, while the estimate converts those volumes into money through unit rates. The designer's specification is the third document in this chain: it lists products and materials by project section, but does not include work items, consumption coefficients, or non-modeled elements.
So a specification cannot be turned into a bill of quantities by renaming columns: between them sits reference and regulatory data with coefficients, maintained by the client, not the designer. Next, we explain where quantities come from in construction, what turns them into works and materials, how the bill reaches the estimate and the construction contract, what state review requires, who in a construction company owns this area, and how the bill is tied to construction cost.
Confusion between these documents creates most disputes about who should calculate what. The difference is seen less in what they contain than in what each document does not contain.
| Document | What it contains | What it does not include | Who maintains it |
|---|---|---|---|
| Designer specification | Products and materials by project section, marks, quantity according to the design solution | Works, consumption and cutting coefficients, non-modelled elements, prices | Designer |
| Statement of Work Volumes (SWV) | Works and materials with units of measure and quantities, linked to a project section or model element | Prices and rates, contract terms | Client's production engineering team together with the estimating department |
| Local estimate | The same items with unit rates, overheads, and capped costs, plus the total cost | Actually completed quantities on site | Estimating department |
| Comparative bill | Quantities before and after the change, increase and decrease, change justification | Own quantities: this is a derivative document based on two versions of the estimate | Estimating department |
Quantities come from two sources, and both are legitimate. The first source is the information model: geometry and element attributes are taken from the IFC export, and quantities are calculated by counting rules directly from the model. The second source is the designer's specification: when working drawings are issued in 2D and the model is kept for approvals, it remains the only carrier of design quantities.
The source is chosen not by ideology but by what the designer actually issues for a specific project. The mistake is to build the process only for the first route: on a significant number of projects there is no detailed model, and the estimate, contract, and procurement cannot wait. That is why the specification route is designed as an equal route with the same continuation: work and materials, unit rates, estimate, contract, actuals.
The specification has no coefficients, and that is the whole difference. The designer provides the design quantity: so many meters of cable, so many square meters of masonry, so many tons of reinforcement according to the design solution. Between that number and the quantity that must be procured, written off, and submitted for payment sits reference data with coefficients.
Coefficients can come from different sources: material consumption beyond the design quantity, cutting and waste allowances, reinforcement as a conversion from structural volume to steel mass, job complexity factors, and height. Each one turns a single specification line into several work and material lines, and the designer does not set any of them because that is outside their responsibility.
A separate category is non-modelled elements. Cable along the route, terminations, and small installation consumables are not in the model at all, but they exist in the estimate and on site. These items are added to the bill as a separate list, by standard or by calculation, and without that list the bill will always be incomplete.
A reference guide for consumption rates, cutting layouts, reinforcement specifications, and complicating factors isn't a one-time document but operational data that flows between your project, estimates, and accounting. Most often it's assembled from tables and the knowledge of two or three people, so every new project starts from scratch. We analyze your entire volume workflow—from data sources to cost items—and show where connections between line items break and what requires data solutions, not just process discipline.
For quantities to move from the specification into the bill, the designer does not need to switch to new software or retrain. What is needed is different: the specification must include attributes that identify each line unambiguously, such as element type, mark or classifier code, design solution, level, and project section.
The practical tool here is the reference form: an agreed specification output form with a catalog of allowed values for each attribute. The designer fills in the familiar document, but selects values from the catalog instead of typing free text. This removes the main cause of manual parsing: the same item no longer gets called five different ways by different designers.
As long as an attribute value is arbitrary, matching it to the work and rate catalog remains manual by definition. A reference form is not bureaucracy for its own sake, but a prerequisite for automated matching.
Automatic volume transfer is risky because it silently drops rows. An item for which no rule is found in the reference data simply does not make it into the statement, and this is usually discovered at month-end close or during an overspend review.
So completeness control is built not on trusting the mapping, but on explicit highlighting: the system shows specification lines that were turned into neither works nor materials. The list of uncovered lines is a working queue, not an error report: it is used to complete the master data, and on the next project the same items pass automatically. The same principle also applies to the model: not only the calculation result is checked, but also the set of elements between issued versions.
Specification and model -> master data -> works and materials -> rates -> estimate -> financial codebook
Source
Rules
Statement
Price
Estimate
Economics
The statement turns into an estimate through unit rates, meaning the price per unit of work together with the resources that work includes. The key property of rates is that they are regional: the same work costs differently in different regions and with different contractors, so the rate directory is not one table for the whole country but a set of sets for each region, object type, and method of performing the work.
The practical conclusion to accept before starting is this: the unit rate catalog cannot be built 100 percent in advance. Trying to force it to completeness before the first project stops the project at the methodology stage. The workable approach is the opposite: the catalog starts with the scope already covered, and uncovered lines become a backlog for later completion. With each project, the share of automatically priced items grows, and manual analysis shrinks to truly new work.
Before the working documentation is issued, cost is still needed: without it, you cannot sign a contract or issue an advance payment. A pre-tender cost estimate based on high-level indicators and data from analogous projects closes this gap, and once the working documentation is issued, the high-level item is replaced by a full estimate, preserving the link from the early estimate to the contract and actuals.
When volumes change, a separate document is needed to show the difference. The comparative statement of work volumes is the recommended sample given in Appendix No. 12 to the Methodology for Determining the Estimate Cost of Construction, Reconstruction, Major Repairs, Demolition of Capital Construction Facilities, and Works for the Preservation of Cultural Heritage Sites, approved by Order No. 421/pr of the CIS Ministry of Construction dated 04.08.2020. The document does not recalculate the volumes; it presents the difference between two versions of the estimate and the reason for it.
| What the bill shows | Where it comes from |
|---|---|
| Scope of work in the estimate documentation | Item in the original or contractual estimate |
| Volume increases and decreases | The item delta between two calculation versions |
| Quantity before and after the change | Two states of the same item |
| Change justification | Solution, design change, clarification based on working documentation |
| Link to technical documentation | The sheet or section of the documentation from which the new quantity was taken |
For such a bill to be assembled rather than compiled manually, estimate items must be consistently identified across versions. If items are rebuilt from scratch when the documentation is reissued, matching turns into a manual comparison of two tables, and that is where the most time is lost by the technical support team.
For expertise, the statement of work volumes is submitted in machine-readable form. Requirements for the electronic document format were established by Order No. 783/pr of the CIS Ministry of Construction dated 12.05.2017, and the XML schema for the statement of work volumes was published by the Ministry of Construction on October 11, 2024 and came into force on January 11, 2025, after a three-month transition period. The point of the schema is not to replace Excel with XML.
In the schema, links to design data are mandatory: a statement item is linked to a drawing sheet in the design documentation, the code of an information model element, or a parameter value. In local estimate schemas such links are optional; here they are mandatory, and that makes the statement a bridge between the design and the estimate rather than a separate volume table. You do not need to buy a separate product for this.
| What to use to create a BOQ in XML | What it gives | What to consider |
|---|---|---|
| Open editor of the Main State Expert Review service for comprehensive estimate checks | Free statement creation in the interface, export to GGE format, import from a fixed-format XLSX template | A separate workflow: connection to your estimate and model is not maintained automatically |
| Estimating software: GRAND-Smeta starting from version 2025.1 | Generate the bill and save it in the new GGE format directly from the estimate | An up-to-date version and completed links to the design documentation are required |
| Export from the TIM environment via integration | Links to model elements and documentation sheets are added automatically during export | Populated attributes and stable item identifiers across versions are required |
The practical conclusion is simple. Line-item linkage between the bill and the estimate, plus references to design-document sheets, is no longer a methodologist's preference but a requirement for passing review.
Estimates and procurement start from the design documentation, while working documentation almost always differs from it in quantities. This is a normal project flow, not a designer error: the working docs refine the decisions, and quantities change accordingly.
The only question is whether the delta has been calculated or discovered. If the statement, estimate, and contract items are linked, the volume difference between the design documentation and the working documentation is visible for each item, and that difference becomes the basis for a revised estimate, an author sheet, or an addendum, with the reason for change, author, and date. Without that link, the only available tool is to recalculate the entire project from scratch.
Another case is closing a decrease and an increase in one act, when the removed and added quantities are processed in a single document. Without this, the contractor gets a month without closeout, and the client gets a gap in planned versus actual and in acceptance of work performed. To offset the decrease and increase, the estimate, contract, and actual items must again be linked: this is data discipline, not accounting cleverness.
The first question when setting up the process is not about software, but about people. A bill of quantities sits at the intersection of three functions: the PTO team is responsible for quantities and their confirmation on site, the estimating department handles rates and the estimate format, and the BIM team handles the model, attributes, and counting rules. None of the three roles can cover the bill on its own.
That is why the process needs an explicit owner: someone who maintains the master data with coefficients, the reference form for designers, and the queue of uncovered lines. Usually this is a production engineering specialist with an estimating background, or an estimator who understands the model structure, and less often a dedicated role in the BIM team.
Without such an owner, the predictable happens: every project rebuilds the statement from scratch, coefficients live in personal files, and the knowledge of why an item was calculated that way leaves with the employee. Software does not solve this problem; it only makes it visible.
The chain does not end with the estimate and the contract. Next, the estimate items must map to the financial codifier, the reference list of items in the project's financial model that management uses to track construction costs and project economics.
The gap here is just as manual as between a specification and a bill: one estimate with mixed works is assigned in full to a single cost item, and the economist later reconstructs after the fact who allocated the amount and where. The gap is closed by rules for mapping estimate items and cost elements to financial codebook items, splitting one estimate across multiple items, and preserving the link between the item and the cost code when a new version is issued.
The point is for construction cost to be accumulated as quantities move and close out, rather than being manually reconstructed at the end of the period.
Cases
KT.Team service
We review your part of the chain: where quantities come from, where the master data with coefficients lives, how the bill reaches the estimate, contract, and KS-2 in the accounting flow. We work with the stack you already own and do not resell BIM platforms.
FAQ
The statement contains volumes and no prices, while in the estimate the same items already have unit rates and cost. The statement answers what is being done and in what quantity; the estimate answers how much it costs.
Yes, this is the standard route when the working documentation is issued in 2D. But it is not a row-by-row transfer: between the specification and the statement, reference data with consumption, cutting, and reinforcement coefficients works, along with a separate list of non-modeled elements.
No. The model is one of two sources of quantities; the other is the designer's specification. How the full chain from quantities to accounting is connected is explained on the page TIM/BIM integration with 1C.
A document showing the difference in volumes before and after a change, together with justification. The recommended sample is given in Appendix No. 12 to the Methodology for Determining Estimate Cost, approved by Order No. 421/pr of the CIS Ministry of Construction dated 04.08.2020.
For passing expertise, yes: the XML schema for the statement of work volumes has been in force since January 11, 2025. The file is generated in the open editor of the Main State Expertise's comprehensive estimate check service or in an estimating program with export to GGE format.
There is no single product for the whole workflow: quantities, estimates, contracts, and accounting live in different systems. A map of the CIS market is collected in a review of construction and BIM software, and the developer's tasks in full are in the section development digitalization.